Delhi: MCD reports 80% progress in pre-monsoon desilting, AAP raises concerns

Published by
PTI

The Municipal Corporation of Delhi (MCD) has completed nearly 80 per cent of the first phase of desilting work in drains measuring four feet and above, with a month still left before the June 30 deadline, officials said on Sunday.

Related Post

Data presented by the civic body showed that 1,12,053.68 metric tonnes (MT) of silt had been removed from 793 major drains against a Phase-I target of 1,41,003 MT as of May 19, taking overall progress to 79.47 per cent.

For drains below four feet, 25,812.99 MT of silt had been removed against a target of 25,850.74 MT, with work nearly complete at 99.85 per cent. This category covers 12,116 drains across the city.

The data showed varying levels of progress across zones in the desilting of major drains.

Civil Lines surpassed its target with 109.08 per cent completion, while Rohini and Keshavpuram recorded more than 97 per cent progress. Najafgarh, which has the highest number of major drains at 133, reported 65.91 per cent progress, while the Central Zone stood at 76.67 per cent and South Zone at 79.74 per cent.

The annual desilting exercise began in February as part of Delhi’s pre-monsoon preparedness measures. More than 13,000 drains under the MCD’s jurisdiction are cleaned every year to improve stormwater flow and reduce the risk of waterlogging during the monsoon.

Meanwhile, the Aam Aadmi Party (AAP) alleged that drain-cleaning work remained incomplete in several parts of the city and warned that Delhi could face waterlogging during the upcoming monsoon season.

MCD Leader of Opposition Ankush Narang claimed that major drains, including Shahdara and Najafgarh, had not been cleaned adequately and questioned whether pending desilting work would be completed before the onset of rains.

“Major drains such as Shahdara and Najafgarh have still not been cleaned. As a result, during the rains, waterlogging will once again be seen on every street and road under the MCD,” Narang said in a statement.

MCD officials, however, maintained that the desilting exercise was progressing according to schedule and would be complete before the monsoon season.

PTI

Published by
PTI
Tags: delhi

Recent Posts

Hydroponic weed worth Rs 4.83 crore seized at Delhi airport; passenger arrested

An Indian passenger arriving from Bangkok was arrested at Delhi’s IGI Airport after customs officials…

June 22, 2026

Rain likely in Delhi

The IMD has forecast thunderstorms and light rain in parts of Delhi, while the city's…

June 22, 2026

Justice delayed in dowry death cases

Low conviction rates and lengthy legal battles continue to frustrate families seeking justice in dowry…

June 22, 2026

Delhi Police rescue man attempting to jump from ISBT Kashmere Gate building

Delhi Police personnel averted a tragedy by rescuing a man who was attempting to jump…

June 21, 2026

PWD undertakes city-wide pothole repair drive ahead of monsoon

Special teams deployed across Delhi to address remaining potholes and prepare roads for the monsoon…

June 21, 2026

NEET-UG retest held at over 5,400 centres in India, abroad amid tight security

Over 22 lakh aspirants appeared for the medical entrance retest, conducted under enhanced surveillance after…

June 21, 2026