Delhi: Several major road repair projects in the national capital are being delayed due to a sharp rise in bitumen prices triggered by the West Asia conflict, officials said on Friday.
With contractors expressing inability to continue road repair work at the previously awarded rates, the Public Works Department (PWD) is now planning to move a proposal before the Expenditure Finance Committee, seeking approval for cost overruns for the ongoing projects.
PWD Minister Parvesh Sahib Singh said the Municipal Corporation of Delhi has already issued a notification approving cost escalation for road projects affected by the bitumen crisis, and the PWD is also considering a similar order.
“Repair and strengthening work undertaken by the PWD on 200-250 kilometres of road has been affected over the last two months due to the steep increase in bitumen prices,” a senior government official said.
Also Read: Khan Market: stories behind a landmark
The projects were originally targeted for completion by March 31, but the deadline has now been extended to July 31,
Six Bangladeshi nationals were sent to a detention centre after overstaying the permitted duration of…
Anshuman Hooda's five-wicket haul and Ayush Badoni's all-round contribution guide South Delhi Superstarz to a…
Judge Anu Grover Baliga has been transferred from the fast-track paper leak court to an…
Inspired by Master Tara Singh's vision, the college brought higher education within reach of refugee…
The IMD has forecast a cloudy sky with light rain in Delhi, while city's air…
India's first junior world squash champion, Anahat Singh now targets Asian Games gold and direct…